Because of the mild weather. 19 MW surplus in Aden electricity generation

English - Friday 17 January 2020 الساعة 10:04 am
aden,newsyemen

The Public Electricity Corporation (CMC) announced a 19 MW surplus in the southern Yemeni city of Aden on Thursday.

According to a bulletin issued by the Control Center for Electricity in Aden, the total generation of power plants reached 208 MW and aden's total load was 189 megaouts, bringing the deficit to 0 mega.

Wednesday's National Control Bulletin recorded a generational surplus of 19 MW.

The State Electricity Corporation noted that the current improvement in power outages and surplus generation in Aden was the result of improved weather conditions and reduced electricity consumption.

According to the control room, this improvement in the continuity of electricity service in Aden is a natural product of the significant improvement in temperature witnessed in Aden starting on Tuesday, which reached 23 degrees.